You are here Projects Sceptre House London

Sceptre House London

sceptre
 

GRH Solutions Limited are responsible for the isolation , decommissioning & disconnection of the existing chilled water pipe work to an existing chiller to the roof at Sceptre House, and the onsite fabrication & installation of new 65mm welded chilled water connections from existing pipe work to the new chiller including all new valves, gauges & test points at the chiller as well as installing new chilled water pump sets & valves within the roof plant room.

We would like to thank H & S support service Limited for awarding us with this project and inpiticular a James Sheehy for his continued help & support.

Main Contractor:
H & S Support Services Limited
GRH Solutions Limited Operatives: 3
GRH Solutions Limited Contract Value: £4993.00

  Breakdown of works:
  • Chilled Water
  • Welding & Prefab
All work was completed to schedule and an exceptional standard.
HSSupport Services

Click the images below to view:

No thumbnails found

<< Back to GRH Solutions project list